Rural driveway and farm dam build
Chatsworth, Gympie region
Project value
approx. $35,000 to $37,000
Scope350 m gravel driveway, drainage and culverts, plus a new 724 m² farm dam.
TerrainRolling hills with steep sections.
The briefThe client needed reliable access to a new house site and a farm dam, delivered within a set budget. We recommended a 100 mm gravel layer. The client chose a 50 mm layer for temporary access, which kept the job affordable and leaves room to top up later.
The challengeThe site had rolling hills and some steep sections. The topsoil was very dry, which created a lot of dust. We ran a water truck throughout the job to keep dust down and to help with compaction.
Driveway- Stripped topsoil along the full 350 m alignment.
- Reused rocky material from the dam dig to build up the driveway from the entrance to the dam wall. Using material from the site kept costs down.
- Reshaped 219 m from the dam wall to the house site, forming a crown and a 300 mm deep table drain on the catchment side.
- Compacted the driveway base.
- Installed four 375 mm culverts, each with a 1 m by 1 m rock apron on geofabric.
- Installed two 6 m long 450 mm pipes, each with a 5 m rock outlet to stop erosion behind the dam wall.
- Laid 114 t of Curra Quarry gravel over the full length.
- Topsoiled the driveway edges.
Dam- A geotechnical engineer tested the material before work began.
- Excavated 2 m across 724 m², leaving a clay base to hold water.
- Built and compacted a 40 m long, 2 m high wall, giving a water depth of about 3.5 m.
- Installed the outlet pipes and rock protection on geofabric.
- Reinstated topsoil on the wall and around the dam.
EquipmentGPS-equipped CAT D6T dozer, 8 t excavator, 60 hp Posi-Track, 12 t padfoot roller and 2.7 t twin drum roller, water truck and tipper.
The resultThe client now has drained, all weather access to the house site and a compacted, engineer checked dam ready to fill. The job was finished in six days and within budget. Headwalls were left for the client to install.